

During a project to install new sewer lines and water mains in a town in Vermont, contractors had to dewater an area where the soil was heavily contaminated with petroleum hydrocarbons.
Carbonair provided a turnkey 500 gpm groundwater treatment system that was able to effectively treat the water and allow the project to proceed without delays.
A Carbonair project manager provided installation oversight and operator training for the system. This system operated at a maximum flow rate of 500 gpm and enabled our customer to complete their project in a timely manner.
At the conclusion of the project our technician mobilized to the site, obtained a spent carbon sample for TCLP testing and shipped the equipment back to our service center for the extraction and disposal of the spent media after receipt of approved documentation.

As part of a major highway improvement project, contractors had to dewater an area in order to pour footings for an overpass. Contaminated groundwater from an adjacent Superfund site was drawn into the dewatering stream, requiring treatment of the contaminated water stream prior to discharge on-site. Based on the large area being excavated, the high water table and the permeability of the soils, a flow rate of 3000 gpm was required to keep the excavation area dry during construction work.
Carbonair first met with the general contractor and environmental engineer to work out the required treatment system design and assess site logistics for system layout, delivery and installation.
Challenges for this project included:
Carbonair designed and provided a 3000 gpm water treatment system consisting of three (3) individual 1,000 gpm treatment streams comprised of the following:
The systems were provided with all necessary components for operation in the field, including 30 horsepower transfer pumps with level controls, hose and fittings, distribution headers and a 100 kW generator for the system’s electrical power requirements. The systems were mobilized, installed and started up in less than five business days from the notice to proceed. The actual field installation took three and one-half days.
The systems performed as designed and allowed the contractor to finish the installation of the footings ahead of schedule, saving them, and the DOT, a considerable amount of money. Carbonair was able to meet their short lead time for delivery of the system and was able to safely deliver, set up and then demobilize the systems in an extremely tight area adjacent to an operating highway and with overhead power lines at the site.
Demobilization was accomplished in just three days.

Carbonair was asked to provide a temporary groundwater treatment system to treat contaminated groundwater that was generated by dewatering performed in support of an underground storage tank removal and upgrade at a gas station in north Florida. In this case, the groundwater at the site was heavily contaminated with petroleum hydrocarbons (gasoline and diesel), which were present in dissolved and free product forms. The groundwater also had high concentrations of Arsenic and other heavy metals. Due to the high water table, the excavation area had to be dewatered at a rate of 500 gpm to allow for the removal of the old tanks and installation of the new tanks. Carbonair designed and provided an on-site groundwater treatment system for a maximum flow rate of 500 gpm.
A Carbonair field crew mobilized, set up, and trained the operators of the system. The system performed as designed, meeting the required discharge limits and treating the water generated at the site at the required flow rate. The use of diesel pumps and Carbonair’s diesel driven air strippers avoided the need for a costly power drop or expensive generator rental. At the conclusion of the project, Carbonair field technicians provided demobilization services including the extraction and disposal of the spent carbon and ion exchange filter media, and demobilization of the equipment.

The former coal gasification plant had operated from 1880 to 1950. The site (see top picture), located adjacent to a major river near a downtown area, was heavily polluted.
Contaminants associated with the old coal gasification plant (primarily coal tars) had seeped into the ground and migrated thirty feet below the water table, into the river sand deposits. Environmental clean-up of the site involved excavation and treatment of 50,000 cubic yards of contaminated soils.
Excavation of the contaminated soils from below the water table next to a major river presented significant challenges. One of the challenges included the requirement for an onsite water treatment plant capable of handling the dewatering discharge.
Carbonair furnished a 2000 GPM temporary water treatment system (see bottom picture) consisting of settling tanks, an oil/water separator and granular activated carbon vessels. Carbonair also furnished all of the required pumps and interconnecting piping.
The system was housed in a temporary sprung structure (shown being erected in the middle picture) during the winter months, to prevent freeze-up.

A mid-Atlantic environmental firm contacted Carbonair to develop a treatment system for a Brownfield development project. Three office complexes were being built in downtown Washington DC. Each building included underground parking, requiring excavation 65 feet below grade.
Groundwater samples revealed BTEX and TCE contamination, and hydrological testing indicated pumping rates of 1000 GPM would be necessary to allow construction to resume.
Water treatment system design challenges on this project included:
For this project, Carbonair designed a modular 1200 GPM water treatment system consisting of twelve 100 GPM units on a common header. Each unit had a duplex bag filter skid and a Carbonair PC13 carbon absorber. Carbonair furnished the complete system, including hose, fittings, headers and valves. Carbonair’s field service team installed the system and trained the operating personnel.

Due to heavy rains from a hurricane, the storm water collection and treatment system in place at a six-hundred acre Superfund site was overflowing. Carbonair was hired to provide a temporary storm water treatment system to avoid fines that may have resulted from unauthorized untreated storm water discharges.
Carbonair responded by providing a 500 GPM temporary storm water treatment system consisting of:
The system was provided with all of the required distribution headers, pumps, hose and fittings.
Carbonair received the customer’s call at 10:00 AM on a Tuesday morning, and responded by delivering a modular 500 GPM treatment system delivered to the site by 8:00 AM Thursday morning. The system was operating by noon on Friday.

Carbonair was hired by a major pipeline company to assist in the clean-up and repair of a ruptured petroleum pipeline in South Carolina. The job was to provide temporary treatment of contaminated groundwater generated as a result of dewatering associated with the repair of the ruptured line.
Carbonair reviewed the contaminant concentrations, required water flow rates and the anticipated duration of the project. Based on this data, we designed, delivered and installed a 250 GPM temporary water treatment system consisting of:
A Carbonair field service technician was provided to oversee the off-loading of equipment as well as assist in set-up, installation and operator training. Carbonair’s Internet-based Monitoring Package (IMP) was provided for remote monitoring and alarm notification.

As part of a highway construction project, contractors had to dewater an area where the soil was contaminated with petroleum hydrocarbons. The contaminated water had to be treated prior to discharge on-site.
Carbonair provided a complete 500 gpm groundwater treatment system consisting of bag filters, granular activated carbon vessels and all interconnecting piping header and hose required for system operation including a totalizing flow meter.
A Carbonair field crew mobilized, set up, and trained the client’s operators of the system to operate the system. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.

Carbonair was asked to provide a temporary groundwater treatment system to treat contaminated groundwater that was generated by dewatering performed in support of an underground storage tank removal and upgrade at a gas station. In this case, the groundwater at the site was heavily contaminated with petroleum hydrocarbons (gasoline and diesel), which were present in dissolved and free product forms. Due to the high water table, the excavation area had to be dewatered at a rate of 800 gpm to allow for the removal of the old tanks and installation of the new tanks. Carbonair designed and provided a rental groundwater treatment system for a maximum flow rate of 800 gpm.
A Carbonair field crew mobilized, set up, and trained the operators of the system. The system performed as designed, meeting the required discharge limits and treating the water generated at the site at the required flow rate. The use of diesel pumps and Carbonair’s diesel driven air strippers avoided the need for a costly power drop or expensive generator rental. At the conclusion of the project, Carbonair field technicians provided demobilization services including the extraction and disposal of the spent carbon, and demobilization of the equipment.

Carbonair was hired by a natural gas utility company to provide a temporary groundwater treatment system to treat contaminated dewatering water in support of the remediation of a Manufactured Gas Plant. As part of the remedy, contractors had to excavate and remove large quantities of soil at the source of the contamination. The soil and groundwater in this area were heavily contaminated with polycyclic aromatic hydrocarbons (PAHs), which were present in dissolved form and as free product. The excavated area had to be dewatered at a rate of 500 gpm during excavation due to the high water table.
Carbonair designed and supplied a rental groundwater treatment system to meet discharge requirements, allow uninterrupted operation and have sufficient capacity to last throughout the excavation period — without media replacement.
Carbonair Field Technicians installed the system, performed system startup and trained customer staff in system operation. In addition, Carbonair provided 24-hour emergency on-call service.
The groundwater treatment system operated as designed on a 24-hour basis for the life of the project without any down time or media replacement required. As a result, the contractors were able to proceed with, and complete, the excavation of the contaminated soil without any delays —saving money and avoiding any costly permit violations.
Carbonair field technicians disassembled and removed the equipment and arranged for the disposal of the spent filter media, completing the “cradle to grave” solution to our customer’s temporary water treatment needs for this project.

Carbonair provided a turn-key mobile water treatment system for this project. The system was utilized at four dewatering locations.
A Carbonair project manager provided installation oversight and operator training for the system. This system operated at 1,500 gpm and enabled our customer to complete their project and return the pipeline to use within their budgeted time line.
At the conclusion of the project the client drained the vessels, obtained a spent carbon sample for TCLP testing and shipped the equipment back to our service center for the extraction and disposal of the spent media after receipt of approved documentation.
Project Specifics:
Carbonair provided and operated a turn-key temporary water treatment system for this project.
A Carbonair field crew mobilized, set up, and trained the client’s field operators to operate the system. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.

Carbonair provided a turn-key mobile water treatment system for this project.
A Carbonair project manager and one technician provided installation and operation of the system at two project locations in Louisiana. The system flow rate was 150 gpm.
At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.

Carbonair provided a turn-key temporary water treatment system for this project.
A Carbonair project manager provided installation oversight and operator training for the system. This system operated at 1,000 gpm and enabled our customer to complete their project and return the pipeline to use within their budgeted time line. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.

Carbonair provided and operated a turn-key temporary water treatment system for this project. A Carbonair field crew mobilized, set up, and operated the system at two locations within a ten day time frame. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.
Project Specifics:
Carbonair provided a turn-key mobile water treatment system for this project.
A Carbonair technician mobilized a truck mounted water treatment system to treat hydrostatic water contained by the customer in frac tanks at two locations. Our technician arrived at each site, made the connections to the tanks and ran the effluent line of the system to the point of discharge.
This system operated at 100 gpm until all water was treated and discharged. This enabled our customer to economically complete their project on time and within budget constraints. At the conclusion of the project demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.
Project Specifics:
Carbonair provided a turn-key temporary water treatment system for this project.
A Carbonair project manager provided installation oversight and operator training for the system. This system operated at 200 gpm and enabled our customer to complete their project and return the pipeline to use within their budgeted time line. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.

Carbonair provided a turn-key temporary water treatment system for this project.
A Carbonair project manager provided installation oversight and operator training for the system. This system operated at 200 gpm and enabled our customer to complete their project and return the pipeline to use within their budgeted time line. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.

Carbonair provided and operated a turn-key temporary water treatment system for this project. A Carbonair field crew mobilized, set up, and operated the system within a four day time frame. This enabled our customer to complete their project and return the pipeline to use within their time line. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.
Project Specifics:
Carbonair provided a turn-key temporary water treatment system for this project.
A Carbonair field crew mobilized, set up, and trained the client’s operators of the system to operate the system. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.

Carbonair provided a turn-key temporary water treatment system for this project. A Carbonair field crew mobilized, set up, and trained the client’s operators of the system to operate the system. At the conclusion of the project Carbonair provided demobilization services including the extraction and disposal of the spent media, and demobilization of the equipment.
Project Specifics:
Site Credits: Ecreativeworks